The Primary Clarifier project is progressing well and is currently approximately 74% complete.
𝐊𝐞𝐲 𝐦𝐢𝐥𝐞𝐬𝐭𝐨𝐧𝐞𝐬
Major construction activities, including excavation, concrete works, piping, electrical installations, and asphalt paving, have now been completed.
The new process and infrastructure were successfully tied in on April 1, 2026, and the system is now operational and nearing the end of commissioning.
Remaining work includes final commissioning activities and minor deficiency and cleanup items before the project closeout phase begins.
𝐓𝐚𝐫𝐠𝐞𝐭 𝐂𝐨𝐦𝐩𝐥𝐞𝐭𝐢𝐨𝐧 𝐃𝐚𝐭𝐞: August 23, 2026
Thank you to the community for your continued support as this important infrastructure project nears completion.