Wastewater Treatment Plant Primary Clarifier Project Update

Steady progress continues on the Primary Clarifier Project, which has now reached approximately 𝟔𝟖% 𝐜𝐨𝐦𝐩𝐥𝐞𝐭𝐢𝐨𝐧 based on the master schedule.

✅𝐊𝐞𝐲 𝐦𝐢𝐥𝐞𝐬𝐭𝐨𝐧𝐞𝐬 achieved include excavation, concrete base, splitter box tie-in, and concrete pours for the clarifier, splitter box, pump gallery, and blending box, along with installation of the clarifier mechanism and cover.

🔜𝐍𝐞𝐱𝐭 𝐬𝐭𝐞𝐩𝐬 include installation of the civil piping and conduits, process mechanical work, and backfilling.
This project will strengthen the long-term reliability and performance of Summerland’s wastewater treatment system and support our growing community.

 