Water Treatment Plant Primary Clarifier Project Update

Jan 22, 2026
Water Treatment Plant Primary Clarifier Project Update
Work continues to progress well on the Primary Clarifier Project, now 54% complete based on the master schedule.

✅ 𝐊𝐞𝐲 𝐦𝐢𝐥𝐞𝐬𝐭𝐨𝐧𝐞𝐬 achieved include excavation, concrete base, splitter box tie-in, and concrete pours for the clarifier, splitter box, pump gallery, and blending box.

🔜 𝐍𝐞𝐱𝐭 𝐬𝐭𝐞𝐩𝐬 include installation of the clarifier mechanism, civil piping, process mechanical work, and backfilling.

This project supports the long-term reliability of Summerland’s wastewater infrastructure.