Water Treatment Plant Primary Clarifier Project Update

Dec 04, 2025
Water Treatment Plant Primary Clarifier Project Update

Work is progressing steadily on the Primary Clarifier Project, which is currently 46% complete based on the project schedule (April 2025–August 2026).

𝐊𝐞𝐲 𝐌𝐢𝐥𝐞𝐬𝐭𝐨𝐧𝐞𝐬 𝐀𝐜𝐡𝐢𝐞𝐯𝐞𝐝
• Excavation for the clarifier, blending box, and splitter box
• Concrete base completed
• Splitter box tie-in
• Clarifier concrete pour
• Splitter concrete pour

• Pump gallery concrete pour

𝐍𝐞𝐱𝐭 𝐒𝐭𝐞𝐩𝐬
• Install clarifier mechanism
• Blending box concrete pour

• Saturation test

This project supports the long-term reliability of Summerland’s wastewater infrastructure.