Water Treatment Plant Primary Clarifier Project Update

Great progress continues on the Primary Clarifier Project — the project is now approximately 𝟔𝟎% 𝐜𝐨𝐦𝐩𝐥𝐞𝐭𝐞 based on the master schedule.

On our social media post, you can view a 360-degree video 🎥showcasing the construction site and providing a full look at the progress from every angle: https://www.facebook.com/share/v/1CBVKiEXis/ or https://www.instagram.com/reel/DU_IpEijuj-/?utm_source=ig_web_copy_link&igsh=MzRlODBiNWFlZA== 

✅ 𝐊𝐞𝐲 𝐦𝐢𝐥𝐞𝐬𝐭𝐨𝐧𝐞𝐬 achieved include excavation, concrete base, splitter box tie-in, and concrete pours for the clarifier, splitter box, pump gallery, and blending box.

🔜 𝐍𝐞𝐱𝐭 𝐬𝐭𝐞𝐩𝐬 include installation of the clarifier mechanism, civil piping, process mechanical work, and backfilling.

This project will strengthen the long-term reliability and performance of Summerland’s wastewater treatment system and support our growing community.

 