Work is progressing steadily on the Primary Clarifier Project, which is currently 46% complete based on the project schedule (April 2025–August 2026).
• Excavation for the clarifier, blending box, and splitter box
• Concrete base completed
• Splitter box tie-in
• Clarifier concrete pour
• Splitter concrete pour
• Pump gallery concrete pour
𝐍𝐞𝐱𝐭 𝐒𝐭𝐞𝐩𝐬
• Install clarifier mechanism
• Blending box concrete pour
This project supports the long-term reliability of Summerland’s wastewater infrastructure.