parks-&-recreation
Discover Summerland
Oct 22, 2025

Primary Clarifier Project - Progress Update

Construction of the new Primary Clarifier is well underway! Here’s an update on progress to date:

𝐖𝐡𝐚𝐭’𝐬 𝐛𝐞𝐞𝐧 𝐜𝐨𝐦𝐩𝐥𝐞𝐭𝐞𝐝 𝐬𝐨 𝐟𝐚𝐫:
✅Excavation for the clarifier, blending box, and splitter box
✅Concrete base completed
✅Splitter box tie-in finished

✅Clarifier concrete pours underway

📊𝐏𝐫𝐨𝐠𝐫𝐞𝐬𝐬: 37% complete

🚧𝐖𝐨𝐫𝐤 𝐮𝐧𝐝𝐞𝐫𝐰𝐚𝐲:
• Forming and pouring clarifier walls

• Forming and pouring the pump gallery

🔜𝐍𝐞𝐱𝐭 𝐬𝐭𝐞𝐩𝐬:
• Construction of the clarifier scum vault

• Splitter box completion

📅𝐓𝐚𝐫𝐠𝐞𝐭 𝐜𝐨𝐦𝐩𝐥𝐞𝐭𝐢𝐨𝐧: August 2026

Contractors are making steady progress with the goal of finishing all underground works before the onset of freezing temperatures.

Thank you for your continued patience as we make important improvements to Summerland’s wastewater infrastructure!

 

Fall Recreation Guide now available: