Construction of the new Primary Clarifier is well underway! Here’s an update on progress to date:
𝐖𝐡𝐚𝐭’𝐬 𝐛𝐞𝐞𝐧 𝐜𝐨𝐦𝐩𝐥𝐞𝐭𝐞𝐝 𝐬𝐨 𝐟𝐚𝐫:

Excavation for the clarifier, blending box, and splitter box

Concrete base completed

Splitter box tie-in finished
Clarifier concrete pours underway
𝐏𝐫𝐨𝐠𝐫𝐞𝐬𝐬: 37% complete

𝐖𝐨𝐫𝐤 𝐮𝐧𝐝𝐞𝐫𝐰𝐚𝐲:
• Forming and pouring clarifier walls
• Forming and pouring the pump gallery

𝐍𝐞𝐱𝐭 𝐬𝐭𝐞𝐩𝐬:
• Construction of the clarifier scum vault
• Splitter box completion
𝐓𝐚𝐫𝐠𝐞𝐭 𝐜𝐨𝐦𝐩𝐥𝐞𝐭𝐢𝐨𝐧: August 2026
Contractors are making steady progress with the goal of finishing all underground works before the onset of freezing temperatures.
Thank you for your continued patience as we make important improvements to Summerland’s wastewater infrastructure!