The District of Summerland is committed to maintaining safe, reliable infrastructure for our community. Here’s the latest update on the Prairie Valley Road and Watermain Upgrades project:

𝐏𝐫𝐨𝐠𝐫𝐞𝐬𝐬 𝐭𝐨 𝐃𝐚𝐭𝐞 / 𝐊𝐞𝐲 𝐌𝐢𝐥𝐞𝐬𝐭𝐨𝐧𝐞𝐬:
• Asphalt paving complete throughout the project
• Multi-use pathway paving finished
• Curbing, watermain, and sanitary sewer installation all complete
• Two major slope upgrades finalized
• Line painting completed

𝐏𝐫𝐨𝐣𝐞𝐜𝐭 𝐒𝐭𝐚𝐭𝐮𝐬:
• Approximately 98% complete based on the master schedule
• Budget spent to date: ~$3,250,000
• Project is nearing the budget ceiling

𝐖𝐨𝐫𝐤 𝐜𝐮𝐫𝐫𝐞𝐧𝐭𝐥𝐲 𝐮𝐧𝐝𝐞𝐫𝐰𝐚𝐲:
• Final project clean-up
• Signage and fence installation

𝐍𝐞𝐱𝐭 𝐒𝐭𝐞𝐩𝐬:
• Complete final clean-up
• Conduct final project walkthrough with the contractor

𝐁𝐞𝐧𝐞𝐟𝐢𝐭𝐬 𝐟𝐨𝐫 𝐑𝐞𝐬𝐢𝐝𝐞𝐧𝐭𝐬:
These upgrades enhance road safety, pedestrian access, and water services for everyone in the community.
Thank you to all residents for your patience and understanding as we complete these important improvements. Your cooperation helps us deliver a better, safer Summerland for everyone.