
Summerland Power
SUMMERLAND POWER SUBDIVISION AND DEVELOPMENT GUIDELINES
-
A PLR (Preliminary Layout Review) and approval to proceed are issued by
Approving Officer. Please see Procedure for Subdivision.
-
Developer is encouraged to approach applicable departments for preliminary
servicing dialogue and information regarding materials supplied by Summerland
Power. A sketch or proposed plan is required.
-
Summerland Power drafts service drawing.
-
Electrical drawing is circulated to an engineering technician and Engineering
and Public Works Superintendent to ensure there are no servicing conflicts.
-
When drawings are approved by the Corporation, copies are submitted to Shaw and
Telus for their design. Applicant will receive confirmation that drawings have
been submitted to other utilities. It is the applicant’s responsibility to
follow up with other utilities to ascertain status of drawings.
-
Telus and Shaw drawings are submitted to the Corporation and reviewed by
Summerland Power and engineering technician. A Corporation-approved copy is
sent back to Telus (Telus requirement).
-
An electrical cost estimate is prepared and submitted to City Hall along with
any other relevant estimates (water, sewer). Deposit in the amount of estimate
is required prior to subdivision/development work to be done.
-
Applicant or agent to contact Summerland Power to arrange a pre-construction
meeting, preferably on site.
-
Primary contractor to apply for excavation permit. This initiates underground
locates. Contractor must supply liability insurance and WCB clearance number on
application. Contractor must either have written company safety policy or use
the Corporation’s safety policy (form to be filled out). This policy will
require an annual update of information.
-
Work to be done by a qualified contractor, ducts to be installed by either an
electrician or certified duct installer. Summerland Power to be contacted for
duct inspection. This also allows Summerland Power an opportunity to take
photographs for records. All road crossings are to be repaired by next business
day. A permit application to BC Safety Authority is required. Upon completion
of works, the electrical contractor is required to submit affidavit (contractor
authorization) and as-constructed drawings to Summerland Power.
-
When work is completed, sign off letter from Shaw and Telus is required.
-
A final inspection is done and deficiencies must be rectified prior to
Corporation signing off final approval.
-
All work must have a one year warranty from the time of substantial completion
and a maintenance agreement must be entered into.
-
All strata developments must provide the Corporation with a blanket electrical
easement.